Clarifies the applicability of the statute of repose for actions arising from construction defects. Clarifies the required contents of a notice of claim of construction defect served on a contractor. Amends the process and time frame for a claimant to accept a contractor's offer to settle or inspect and authorize the contractor to proceed with repairs. Limits the amount a claimant can recover if the claimant rejects a contractor's reasonable proposal for inspection or a reasonable offer to remedy. Clarifies the consequences of rejecting an offer of settlement. Effective 7/1/2050. (SD1)