States / California / SB 440

SB 440 Enacted

Private Works Change Order Fair Payment Act.

Introduced
In Committee
Floor
Crossed Over
Passed
Enacted

Existing law contains various provisions relating to contracts for the performance of private works of improvement, including provisions applicable to a retention withholding by an owner from a direct contractor or by a direct contractor from a subcontractor.

This bill would establish, until January 1, 2030, for contracts entered into on or after January 1, 2026, a claim resolution process, as specified, applicable to any claim by a contractor or subcontractor, as described, in connection to a work of improvement or site improvement, except as specified. The bill would define a claim for these purposes as a separate demand by the contractor or subcontractor, as described, sent by registered mail or certified mail with return receipt requested, for, among other things, a time extension for relief from damages or penalties for delay assessed by an owner under contract for a work of improvement or site of improvement. The bill would make related findings and declarations.

Chamber
Senate
Introduced
Feb 18, 2025
Last action
Oct 10, 2025 — Chaptered by Secretary of State. Chapter 583, Statutes of 2025.
Session
20252026
Momentum
86 · Very high